Every once in a while when I mark a task done the actual completion date reflects the date the task was planned to be completed not the date I marked it complete. | Community
Skip to main content
Level 4
July 18, 2020
Question

Every once in a while when I mark a task done the actual completion date reflects the date the task was planned to be completed not the date I marked it complete.

  • July 18, 2020
  • 2 replies
  • 434 views

The planned start date and completion date are in the future so when I mark a task complete both the actual start date and actual completion date reflect that future date. What changes do I need to make on the task setup to ensure that the actual start date and completion date are accurate?‚

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

imgrund
Adobe Employee
Adobe Employee
July 19, 2020

Hi Frank - there is a global setting for this in the Setup area (see below). Weird though that it is only happening to some of your tasks and not all. That seems to be a bug to me.

FrankFoAuthor
Level 4
July 26, 2020

‚Thanks Anthony I believe our administrator is going to make the adjustments. When they make the adjustment do I need to create a new project or will the change take effect for all tasks and issues going forward?