Hi there,

 

Is there a way or a workaround to duplicate a program that contains the same projects that are updated on a quarterly timeline?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Sven-iX

Unless you use Fusion it's manual steps - duplicate the program, rename it, then copy each project, and finally bulk edit all copies and change to the new program. 

2 replies

Srinija_N
Level 7
March 13, 2025

As far as I believe there is no option 'Copy' for Program object. This could be possible through Fusion automation..

Sven-iX
Community Advisor
Sven-iXCommunity AdvisorAccepted solution
Community Advisor
March 13, 2025

Unless you use Fusion it's manual steps - duplicate the program, rename it, then copy each project, and finally bulk edit all copies and change to the new program.