Display most recent Task Update in a Calculated Field
Hello! Is it possible to display the most recent user Update in a calculated field? Here is a typical example from my org: User A makes a task Update ("files are ready for client review. Here is the link to folder xyz") then completes her task. User B is then prompted to start his task and needs visibility into User A's update. I'd like to be able to display User A's update in a calculated field that populates on User B's Work List so he doesn't have to navigate back to User A's task to read her last Update. Thoughts?