DayDiff between TODAY and Project Planned Start Date | Community
Skip to main content
Level 4
March 3, 2025
Solved

DayDiff between TODAY and Project Planned Start Date

  • March 3, 2025
  • 2 replies
  • 518 views

I am trying to amend a report of Tasks that will pull a field to show the difference in days between Today ($$TODAY) and Project Planned Start Date.

Can anyone help me with the Text Mode for the report or a calculated field?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by ThomasNe2
WEEKDAYDIFF($$TODAY,{project}.{plannedStartDate})

2 replies

ThomasNe2AuthorAccepted solution
Level 4
March 3, 2025
WEEKDAYDIFF($$TODAY,{project}.{plannedStartDate})
KellieGardner
Community Advisor
Community Advisor
March 3, 2025

for a task report it would be:

 

 

displayname=Week Day Difference valueexpression=WEEKDAYDIFF($$TODAY,{project}.{plannedStartDate}) valueformat=HTML

 

 

 

WEEKDAYDIFF(date2, date1)