Change Order/Documenting Iterations - How do you do it? | Community
Skip to main content
Level 2
October 4, 2022
Question

Change Order/Documenting Iterations - How do you do it?

  • October 4, 2022
  • 5 replies
  • 1105 views

We are looking to implement a process to document the number of iterations a project/request has gone through based on feedback/changes from our requestors/reviewers. I was thinking of adding a custom form for the project managers to track iterations as it would become a reportable field. Any other processes or ideas that have worked for you/your org?

 

Thank you! 

Kate Tomaszek 

katherine.tomaszek@thehartford.com

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

5 replies

ElliotLeson
Level 3
October 4, 2022

I created a template with a custom form that is used for Change Orders.

When a change order is needed they drop in the template and fill out the custom form.

Parent Task: CHANGE ORDERS

Child Task: Change Order #1

Child Task: Change Order #2

 

The task and custom form now have reportable infromation and the info stays within the project for one source of truths.

 

Level 2
October 4, 2022

Thanks for your reply! Do you apply a standard duration for the change order tasks that are added? Or is it up the project manager to modify the dates of the task to properly reflect the work and schedule? 

ElliotLeson
Level 3
October 4, 2022

No problem. The change order tasks are for the change order only.

Duration has a standard SLA of .25 days and typically takes less than 15 mintues to enter the information. 

 

I believe the additional information you may be looking for is Rounds/Iterations.

We have tasks for Rounds and depending on the Task, Client, and Deliverable each has their own duration and planned hours (our Master Templates have a generica duration and planned hours as placeholders). I can provide more information on templates if needed.

Example.

RD 2 CREATIVE DEVELOPMENT
[RD2] Copy Development
[RD2] Design Development
[RD2] Team Review
[RD2] Internal Review
[RD2] Proofreading
[RD2] Complete Proofreading Edits
[RD2] Account Sign-Off
[RD2] Internal Partner Review
[RD2] Internal Partner Feedback