November 1, 2016
Question

Booking group or team time-off

  • November 1, 2016
  • 11 replies
  • 1846 views
When a resource books a time-off, Workfront blocks any "booking request" for such a resource during the time the resource is off. I really like that! Is there a way to book a team or group time-off for the time when the company is off for Stat Holidays? In MS project, you can modify project working time to exclude any activity in those particular dates. Can this be done in Workfront? Thank you. Sergio Iturri | Project Manager & Scrum Master siturri@nonlinear.ca | work: 647.776.2559
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

11 replies

Level 10
November 3, 2016
Btw, line 4 below should say: 4) If you assign multiple users to a task, it looks at your Setup-Project Preferences-Timelines Multiple User setting (see above) to know whether to use the calendar of the primary assignment or the project calendar; Sorry about that… Eric