Avoid Parent Tasks in Task Report
Hello Friends, I created one task report to collect all planned hours for year 2019 in our department. So, added all portfolios. But in the result, it also pulls the parent task. Which increases the planned hours significantly. I have attached a screen shot for your kind reference. Could you please help to correct it. Also I tried to add below filter options, but many tasks which are not as parent task they also get removed. Later I removed these filter options. Task>Assigned to ID Task>No. of children>Equal Case Sensitive>0. Looking for your expertise. Kind regards, Kundan. Kundan Kumar KGON - (Kverneland Group Operations Norway AS)