Allocating for Off Site Video Shoots
Situation
- Our video team travels a few times a month for video shoots. Most of the time when they are on shoots, they are not available to work on other projects. Our current process is to add a task for the shoot and assign each videographer a full day’s worth of hours (6 hours in this case) to account for this time.
Problem
- Other projects / tasks are still being scheduled during their “shoot days” so this causes them to be overallocated because if hours for another project were already allotted to those days prior to assigning a shoot, then Workfront wouldn't know to prioritize the shoot hours and rearrange the hours of the other task(s) that landed on those days.
One solution that we thought of is for the team to block it off as an out of office day, but then they wouldn’t be able to log hours / account for the shoot day. If you could provide best practice / insight here, we would appreciate it!
Thoughts?