"Actual" Actual Completion Date
With our use case, Projects are reopened sometimes seasonally as more information is added to them that needs to be completed. When we reopen Projects, we adjust the Planned Completion Date to reflect the new deadline. Unfortunately, when trying to build reporting on these dates, it shows the first Actual Completion Date, not the most recent. Is there any way to have it pull the most recent? I am currently using a Task report as I have to include some specific Task dates as well.
Added info: Project Details reflects the newest Actual Completion Date. I found it was pulling the original by looking at the Updates.
Thank you!