Do flow steps still execute when trigger campaign is de-activated? | Community
Skip to main content
November 16, 2016
Question

Do flow steps still execute when trigger campaign is de-activated?

  • November 16, 2016
  • 1 reply
  • 3021 views

Hello all.


Just a quick question.... I have been working on the assumption that when you de-activate a trigger campaign you are effectively turning it off.

Recently I have realized (Unless its a bug) that leads in a wait step are still processed even through the campaign has been deactivated????

It sort of makes seance although a little counter intuitive to a newbie. Can someone please confirm if this is the case.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Devraj_Grewal
Level 10
November 16, 2016

Deactivating a trigger campaign will prevent new leads from qualifying for the smart list and subsequently entering the flow. However, leads in the flow will still continue to execute those steps.

November 16, 2016

Thanks for the response. So what is best practice from preventing leads from executing.

At the moment all I can think of is, deleting the flow steps or using remove from flow. Is there a simple way to just turn off the campaign?

Devraj_Grewal
Level 10
November 16, 2016

You can abort the campaign. Here is a great reference: Product Docs