Parent Task Duration Showing in Hours Instead of Days

  • July 21, 2021
  • 2 replies
  • 1524 views

I am having an issue with Parent Task Durations. They are currently showing in hours and I cannot figure out how to change them. I have no desire to see that a phase of my project is 1135 hours...but would love to see how many days it is! Is there a setting I am missing somewhere?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by MartyGa3

Parent Tasks duration units can be changed by simply type 0d in the duration field to change it to days. Since the duration is a rollup, this will not affect the calculation, only change the unit.

2 replies

MartyGa3Accepted solution
Level 2
July 21, 2021

Parent Tasks duration units can be changed by simply type 0d in the duration field to change it to days. Since the duration is a rollup, this will not affect the calculation, only change the unit.

CoriStAuthor
Level 2
July 21, 2021

Thank you, that worked great!

Doug_Den_Hoed_AtAppStore
Community Advisor
Community Advisor
July 21, 2021

Slick trick! Thanks Marty -- duly noted!