Yet another question! I'm finding that with cross-project predecessors, "update on change" does not automatically change (recalculate) successor task dates when dates on the predecessor tasks are changed. One has to manually recalculate the timeline or wait overnight. I want to be that this is working as intended. If so, I'm going to submit an idea that it be made so.

Thanks!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Doug_Den_Hoed_AtAppStore
Community Advisor
Community Advisor
February 3, 2021

Hi Jason,

Yep, As Designed, as I understand it; one of several reasons we created our Force Timeline solution, which provides a simple, schedulable way to automatically recalculate the timelines for all projects matching a selected filter, ensuring they are up to date.

Regards,

Doug

Learn more at www.atappstore.com, email doug.denhoed@atappstore.com, or tag me here @Doug_Den_Hoed_AtAppStore.
JasonLe4Author
Level 2
February 4, 2021

Ok, that's what I figured. Thanks for your help Doug!