Why is my project showing "at risk", when its not scheduled to BEGIN for another month?!?!?!


I have several projects showing up on my people's task lists as late, but are not scheduled to begin for several weeks. This project is showing up in my "At Risk" report as well. WHY?!?! 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Kurt_Jones
Kurt_JonesAccepted solution
Adobe Champion, Community Advisor, UG Leader
October 28, 2025

n8rt8r,

This article explains how the conditions are calculated to provide a better understanding, https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/projects/plan-a-project/project-progress-status.  It graphic for each helps, I've used that to make a view so I could all those dates myself, as I didn't fully understand.

If my response answered your question, please mark it answered, so others can find the answer

2 replies

Kurt_Jones
Adobe Champion, Community Advisor, UG Leader
Kurt_JonesAdobe Champion, Community Advisor, UG LeaderAccepted solution
Adobe Champion, Community Advisor, UG Leader
October 28, 2025

n8rt8r,

This article explains how the conditions are calculated to provide a better understanding, https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/projects/plan-a-project/project-progress-status.  It graphic for each helps, I've used that to make a view so I could all those dates myself, as I didn't fully understand.

Translate
If my response answered your question, please mark it answered, so others can find the answer
KellieGardner
Community Advisor
Community Advisor
October 28, 2025

My assumption, without being in your system and seeing the whole project, is that someone is committed to having something done by clicking on work on it or by marking a task in progress, so that task is already in progress and is 0% complete. So, it's likely throwing off your projected, estimated dates.