I've looked through Workfront One resources and I couldn't find why certain tasks appear in Blue and others appear in Pink on the gantt chart and I've been asked to provide an answer, can anyone help explain why there's a color deviation on how tasks appear in the gantt chart? Do the colors represent anything? To us, it seems pretty random what color each task is assigned but we want to make sure we're not missing any visible cues.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by Doug_Den_Hoed_AtAppStore

Hi Naushin,

Pink means Critical Path (ie “driving” the Project Completion Date), and can be toggled off (blue) under the option “gear box” button at the top left of the Gantt Chart.

Regards,

Doug

2 replies

Doug_Den_Hoed_AtAppStore
Community Advisor
Doug_Den_Hoed_AtAppStoreCommunity AdvisorAccepted solution
Community Advisor
August 11, 2020

Hi Naushin,

Pink means Critical Path (ie “driving” the Project Completion Date), and can be toggled off (blue) under the option “gear box” button at the top left of the Gantt Chart.

Regards,

Doug

Learn more at www.atappstore.com, email doug.denhoed@atappstore.com, or tag me here @Doug_Den_Hoed_AtAppStore.