Variance calculation

Hi Team, 

 

Can anyone help me, what would the calculation be for  variance in weekdays between baseline Task planned start date and task planned start date?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

lgaertner
Level 9
Aug 29, 2024 10:49 AM UTC

Hello Namratha,

 

although I did not work with Baselines yet, according to the API-Explorer this should help:

 

WEEKDAYDIFF({defaultBaselineTask}.{plannedStartDate},{plannedStartDate})

 

Regards

Lars

Translate
Level 2
Sep 5, 2024 7:01 PM UTC

Very sorry for the late reply. This works well! Thank you so much.