Any suggestions on how best to capture and track the # of artwork rounds within a project plan in Workfront?  Ideally, capture the rejection reasons as well. Thank you

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Heather_Kulbacki
Heather_KulbackiAccepted solution
Community Advisor
Dec 19, 2022 1:17 PM UTC

We count the number of times the creative went out to our business partners for review by the number of business review tasks on a project.

  • If the project requires more rounds than we have built into the project template, we have an additional template with just a task for the revisions and a task for another business review that can be added in
  • If the project doesn't need all the rounds that are built into the template, the project manager can delete the extra tasks

I suppose we could add a custom form to our business review task for someone to fill in the rejection reason for each round that was rejected, then pull that into a report with the task.

8 replies

KellieGardner
Community Advisor
Community Advisor
Dec 14, 2022 9:38 PM UTC

We used document version to track rounds of changes. Never tried pulling in the rejection reasons though.

Translate
keri13Author
Level 2
Dec 16, 2022 5:58 PM UTC

Hi Kellie,

Thanks so much for your reply!  So that I'm clear, you track rounds by document versioning but you're not capturing # of rounds in any way in Workfront, is that correct? Our goal is to get the # of round info into WF in some way for reporting purposes.

Translate
KellieGardner
Community Advisor
Community Advisor
Dec 19, 2022 3:26 PM UTC

Correct, we just use a report that captures how many versions of a document were loaded to signify revisions. So if a document has 6 versions - we can assume 1 was the original upload so a total of 5 rounds of revisions were done.

 

The only other way I can think to  capture it in reporting would be to use a custom form and have someone put in how many revisions were done. 

Translate
Heather_Kulbacki
Community Advisor
Heather_KulbackiCommunity AdvisorAccepted solution
Community Advisor
Dec 19, 2022 1:17 PM UTC

We count the number of times the creative went out to our business partners for review by the number of business review tasks on a project.

  • If the project requires more rounds than we have built into the project template, we have an additional template with just a task for the revisions and a task for another business review that can be added in
  • If the project doesn't need all the rounds that are built into the template, the project manager can delete the extra tasks

I suppose we could add a custom form to our business review task for someone to fill in the rejection reason for each round that was rejected, then pull that into a report with the task.

Translate
keri13Author
Level 2
Dec 20, 2022 8:06 PM UTC

Thanks so much for your reply Heather! Very helpful.

Translate
Madalyn_Destafney
Community Advisor
Community Advisor
Jan 6, 2023 9:12 PM UTC

Hi there, I actually just posted something related to this in this thread - https://experienceleaguecommunities.adobe.com/t5/workfront-discussions/from-eoy-reporting-workshop-continued-discussion-on-actual-vs/m-p/563482#M203 - the top comment in the thread. Hopefully this helps!

Translate
If this helped you, please mark correct to help others : )
keri13Author
Level 2
Jan 10, 2023 1:51 AM UTC

Thanks Madalyn!