Task Approval report

  • September 18, 2026
  • 1 reply
  • 31 views

Hello -

Need help to create task approval report with name who approved it, approval date and time, approval status, and any comments entered during the approval process, creating a complete audit trail.

 

 

1 reply

Madalyn_Destafney
Community Advisor
Community Advisor
September 18, 2026

Start by going to the Reports page and select the Approval Process report type. Your first filter will be for approval process > approval objCode >/equal > Task. Now you have it filtered to task approvals and you can add any other filters there like name of task approval flows and other things. The columns you want are pretty standard, can add approval statuses, etc. But the approval process report type with that first filter will start you in the right direction : )