I would like to create a report that provides the dates or elapsed days between status changes on a project. For example, days between Current to Pending Approval, Pending Approval to Pending Implementation, Pending Implementation to Closed. We would like to identify where significant delays occur within projects occurred. Suggestions?
Questo argomento è stato chiuso alle risposte.

71 risposte

Level 2
January 3, 2019
Did anyone figure out how to make this work? I am struggling to make a similar report. I tried listing Audit Text and Note Text on a test project without any filters other than project id. It still does not list anything for project status changes. It only lists changes for tasks and issues. Is this a Workfront bug? or there is some alternative way to fetch the project status change. Sadashiv Kulkarni