Seeing $0 in planned labor costs on templates and projects

Has anyone seen where a template task has an assignment and planned hours and the planned labor cost is at a $0 even if the assignee has a job role with a cost per hour? It is also not consistent some tasks with the same assignee do have a cost. 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
skyehansen
skyehansenAccepted solution
Jun 6, 2024 4:31 AM UTC

there's a setting on every task called "Cost Type". Is it possible that some of your tasks have "no cost" as the cost type?

2 replies

skyehansen
Adobe Champion and Community Advisor
skyehansenAdobe Champion and Community AdvisorAccepted solution
Jun 6, 2024 4:31 AM UTC

there's a setting on every task called "Cost Type". Is it possible that some of your tasks have "no cost" as the cost type?

Translate
Level 3
Jun 6, 2024 4:19 PM UTC

Oh thank you! I thought I was going crazy