How to link risks to tasks within a project plan

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Doug_Den_Hoed_AtAppStore
Doug_Den_Hoed_AtAppStoreAccepted solution
Community Advisor
Apr 7, 2023 4:15 PM UTC

 

Hi @aswi,

 

Since the native Risk object does not (yet) support custom data and is only available at the Project level (where you're interested in Task level), one common approach is to instead use the native Issue object instead (and as there are four built in, you could rename one to "Risk", if you wish).

 

Regards,

Doug 

Learn more at www.atappstore.com, email doug.denhoed@atappstore.com, or tag me here @Doug_Den_Hoed_AtAppStore.

1 reply

Doug_Den_Hoed_AtAppStore
Community Advisor
Doug_Den_Hoed_AtAppStoreCommunity AdvisorAccepted solution
Community Advisor
Apr 7, 2023 4:15 PM UTC

 

Hi @aswi,

 

Since the native Risk object does not (yet) support custom data and is only available at the Project level (where you're interested in Task level), one common approach is to instead use the native Issue object instead (and as there are four built in, you could rename one to "Risk", if you wish).

 

Regards,

Doug 