Skip to main content
MegSVT
Level 4
September 17, 2024
Question

Restrict Standard License (program manager) from Updating Project Completion Date

  • September 17, 2024
  • 4 replies
  • 736 views

With the updated Light, Contributor, & Standard License, I now have Program Managers going into jobs and adding tasks (which I have figured out how to disable) and updating the project completion date (which I cannot figure out without changing the license). The light license is too "light" and therefore they cannot complete tasks which I need them to be able to do. We cannot have dates and timelines being changed without approval. How do I fix this? 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

4 replies

KellieGardner
Community Advisor
Community Advisor
September 17, 2024

I'm not on the new license types yet but it sounds like it's a permission based thing where they have manage access to the project which allows full access. You can typically limit access through the projects/templates or in the sharing permissions. 

 

 

RandyRoberts
Community Advisor
Community Advisor
September 17, 2024

For the OP's reference:

https://experienceleague.adobe.com/en/docs/workfront/using/basics/grant-request-object-permissions/share-a-project

 

Project permission options

The following table lists the permissions that users can grant when sharing a project. 

Actions Manage Contribute View
ActionManageContributeView
Add Custom Form✓  
Update Custom Fields✓✓ 
Add An Approval Process✓  
Approve a Project✓✓✓
Approve hours✓✓ 
Create A Project✓  
Add Document(s)✓✓✓
Add Issue(s)✓✓✓
Add Task(s)✓✓ 
Copy Project ✓ 
Delete Project✓  
Modify Planned Dates✓  
Share Project✓✓✓
Share System-wide  ✓
View Project✓✓✓
Updates/ comments✓✓✓
Change Status✓  
Log Hours✓✓ 
Edit Assignments✓✓ 
Manage Baseline✓  
Manage Risks*✓  
Manage Finance*✓  
Add/ Edit Expenses*✓✓ 
View Finance*✓✓✓
Attach Template✓  
Save As Template✓✓✓
Add/ Edit Business Case✓  
Edit Project Details✓  
Edit Staffing✓  
Export to MS Project✓✓✓
Recalculate Finance/ Timeline*✓  
Set Queue Properties✓  
Edit Project in Bulk in a List✓  
MegSVT
MegSVTAuthor
Level 4
September 17, 2024

I can't seem to locate where you can address permissions system wide - do you have to do this on every project that gets assigned out?