Resources, Durations and Planned Hours are Blank for Sub-Task

Hi Community, 

I'm trying to create a report to pull sub-tasks with Blank resources, or Durations or Planned hours. The purpose of this report is to ensure project owners or PMs don't leave any sub-task blank during project planning. 

Below (screenshot) is the report I created but is not working as expected, is pulling parent task and sometimes it does NOT pull sub-task that has no resources, or durations or planned hours. 

Any help on what filters to apply will be much appreciated. 

Thanks 

 

 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Ryzan99Accepted solution
Level 2
Aug 21, 2023 3:06 AM UTC

Hi. Have you tried including "Task > Number of Children" within both the first and last logic? Since you're using an OR statement, you also need to include the same filter (Task > Number of Children) in the other logic. Please refer to the example screenshot. I hope this solution helps you.

 

5 replies

Ryzan99Accepted solution
Level 2
Aug 21, 2023 3:06 AM UTC

Hi. Have you tried including "Task > Number of Children" within both the first and last logic? Since you're using an OR statement, you also need to include the same filter (Task > Number of Children) in the other logic. Please refer to the example screenshot. I hope this solution helps you.

 

Translate
meshackOmAuthor
Level 3
Aug 23, 2023 1:24 AM UTC

Thank you so much @ryzan99  and @kundanism , your input was very valuable and it works. Please see the filters I used as per your input. Your help is super appreciated. 

 

 

Regards,

Mesh 

Translate
Level 2
Aug 28, 2023 6:11 AM UTC

You're welcome, @meshackom.

Translate
Kundanism
Level 10
Aug 21, 2023 9:27 AM UTC

May be you can try this one. Please refer the attachment. Believe matches your requirement criteria.

Translate
meshackOmAuthor
Level 3
Aug 23, 2023 1:24 AM UTC

Thanks @ryzan99 ! 