Has anyone created a cycle time report for the amount of time it takes from request to project conversion?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
SuryaLakhani
SuryaLakhaniAccepted solution
Level 4
Apr 8, 2025 3:17 PM UTC

Hi,

 

You should be able to do this at the project level with DATEDIFF, both in a report or a calculated field:
ROUND(DATEDIFF({entryDate},{convertedOpTaskEntryDate}),2)

2 replies

SuryaLakhani
SuryaLakhaniAccepted solution
Level 4
Apr 8, 2025 3:17 PM UTC

Hi,

 

You should be able to do this at the project level with DATEDIFF, both in a report or a calculated field:
ROUND(DATEDIFF({entryDate},{convertedOpTaskEntryDate}),2)