Report to identify cross-project dependencies

  • September 24, 2020
  • 2 Antworten
  • 687 Ansichten

Hi WF Community,

Does anyone know if it's possible to filer a report (e.g. task report) based on tasks that have cross-project predecessors?

Can't seem to find an appropriate field within a task report for cross-project dependencies.

Thanks.

Nick

Dieses Thema wurde für Antworten geschlossen.
Beste Antwort von AdinaPi1

Try this (updated after posting)

predecessorsMM:name_Mod=notblank

predecessorsMM:projectID=FIELD:projectID

predecessorsMM:projectID_Mod=ne

2 Antworten

AdinaPi1Antwort
Level 9
September 24, 2020

Try this (updated after posting)

predecessorsMM:name_Mod=notblank

predecessorsMM:projectID=FIELD:projectID

predecessorsMM:projectID_Mod=ne

NickVa7Autor
Level 9
September 25, 2020

That worked. Thanks, Adina!