Quick Tip: You can add a column to a project view to see the total number of tasks in each project.

To see the total number of tasks in each project, add the following text mode code to a blank column in your view:

valuefield=totalTaskCount

linkedname=direct

valueformat=int

displayname=Total Tasks

textmode=true

querysort=totalTaskCount

"Like" this post if you find it helpful!👍

To find all previous Quick Tips, go here and view the Discussions tab.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Heather_Kulbacki
Community Advisor
Community Advisor
Jul 7, 2023 7:17 PM UTC

Exactly what I needed this afternoon!!

Translate
Level 4
Feb 7, 2024 11:58 AM UTC

Hi there

Is there an easy way for this to convert to only Open Tasks? Those that are not 100% complete?

Thomas

Translate