Project timelines

If dates shift forward or back, how can we tell the difference in Workfront? Currently we are changing the date and adding a note in the description section but there has to be a better way to show change in the project once complete.

 

 

 

 

 

 

 

 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

Madalyn_Destafney
Community Advisor
Community Advisor
Aug 5, 2023 12:00 AM UTC

Hi, have you considered project baselines?

Basically allows you to compare what the project initially was versus what it ended up as. More info here: https://experienceleague.adobe.com/docs/workfront/using/manage-work/projects/create-projects/create-baselines.html?lang=en 