Very soon, Workfront is releasing a feature where calendars have the option to ignore Actual Dates completely (YAY!!!) I'm curious, would people prefer the default to be No or Yes?
Dieses Thema wurde für Antworten geschlossen.

3 Antworten

June 9, 2020

This is great to hear as this has been a major issue for my team. Can you confirm if this will be rolled out in Workfront classic and when the date will be?

imgrund
Adobe Employee
imgrundAdobe EmployeeAutor
Adobe Employee
June 9, 2020

Hi - The release notes say it will be rolled out into Production June 18th and will be in both Classic and NWE: https://one.workfront.com/s/article/20-3-release-overview-760883140?language=en_US

It also looks like on June 18th, you will be able to use custom dates too instead of planned, projected, and actuals.

Now, can I confirm all this will actually happen, no. I'll leave that up to Jeremy and team. ;)

jerflo
Adobe Employee
Adobe Employee
June 9, 2020

Love the excitement behind these new capabilities! Yes, both new features will hit Production on June 18th. We will support both Workfront Classic and NWE.