My Assigned Tasks report filtering out "Done with my part"?

All my users have an assigned tasks report that filters tasks that are not complete where they are one of the assignees. However, when the task has multiple assignees and each one clicks "done with my part" the task stays in their report until the final person is done and has completed the task. Does anyone know any other completion type of field that is activated on a per-assignee basis that I could be using instead?
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

5 replies

Level 9
Dec 29, 2016 1:10 PM UTC
This "https://community.workfront.com/p/fo/st/topic=62&post=3457#p3457" thread may help.
Translate
SkyeHaAuthor
Level 10
Dec 29, 2016 4:49 PM UTC
Thanks Greg! I will give it a shot. I had been hoping to be able to refine the report I already have but the important thing is that my users get whatever they want ;-)
Translate
Madalyn_Destafney
Community Advisor
Community Advisor
May 2, 2023 12:49 PM UTC

Hi there! You're not the first person to post about this. There was no Idea to be able to do this easily, so I've created one here to please upvote! https://experienceleaguecommunities.adobe.com/t5/workfront-ideas/filter-out-completed-done-with-my-part-tasks-in-task-report/idi-p/590722#M22051

Translate
If this helped you, please mark correct to help others : )
Adobe Employee
Feb 21, 2024 5:55 PM UTC

Hi Madalyn,

Is there a way to do this now?

Translate
Madalyn_Destafney
Community Advisor
Community Advisor
Feb 29, 2024 6:22 PM UTC

No, but I had ended up modifying my task reports to exclude those that were still not done by the other assignee but were clicked 'done with my part' from the user viewing the report. Here's the text mode, of course you'll need to revise as needed:

'My' Tasks Due Today or Earlier, Removes Tasks I’ve Marked Done With My Part
EXISTS:1:$$OBJCODE=ASSGN

EXISTS:1:assignedToID=$$USER.ID

EXISTS:1:status=DN

EXISTS:1:status_Mod=notin

EXISTS:1:taskID=FIELD:ID

OR:1:assignmentsUsersMM:ID=$$USER.ID

OR:1:assignmentsUsersMM:ID_Mod=in

OR:1:personal=true

OR:1:personal_Mod=eq

OR:1:plannedCompletionDate=$$TODAY

OR:1:plannedCompletionDate_Mod=lt

OR:2:isComplete=false

OR:2:isComplete_Mod=eq

OR:2:numberOfChildren=0

OR:2:numberOfChildren_Mod=eq

OR:2:plannedCompletionDate=$$TODAY

OR:2:plannedCompletionDate_Mod=lte

OR:2:project:statusEquatesWith=CUR

OR:2:project:statusEquatesWith_Mod=in

OR:2:teamID=$$USER.teamIDs

OR:2:teamID_Mod=in

assignmentsUsersMM:ID=$$USER.ID

assignmentsUsersMM:ID_Mod=in

isComplete=false

isComplete_Mod=eq

numberOfChildren=0

numberOfChildren_Mod=eq

plannedCompletionDate=$$TODAY

plannedCompletionDate_Mod=lte

project:statusEquatesWith=CUR

project:statusEquatesWith_Mod=in

Translate
If this helped you, please mark correct to help others : )