Marking work complete with light license

Is it possible to mark task work complete if you only have Light license level?  Is this only possible if you have a Standard license level even if you have manage or contribute access to a project? 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Daniel_Clarke
Daniel_ClarkeAccepted solution
Adobe Champion and Community Advisor
Jan 13, 2025 9:59 PM UTC

@bethholzman you are correct, Light users cannot mark work complete.

Access level documentation includes this note:

"Users with the Light access level:

  • Can be assigned work items but can’t complete them."

Forces users who will be actively working on projects into the Standard License type.  

1 reply

Daniel_Clarke
Adobe Champion and Community Advisor
Daniel_ClarkeAdobe Champion and Community AdvisorAccepted solution
Adobe Champion and Community Advisor
Jan 13, 2025 9:59 PM UTC

@bethholzman you are correct, Light users cannot mark work complete.

Access level documentation includes this note:

"Users with the Light access level:

  • Can be assigned work items but can’t complete them."

Forces users who will be actively working on projects into the Standard License type.  