Question

Looking to create some special reports

Looking to create a report that displays hours recorded by worker for a specific week. I am also looking to create a report that displays time recorded to each individual task by project.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Doug_Den_Hoed_AtAppStore
Community Advisor
Community Advisor
Nov 10, 2020 11:28 PM UTC

Hi Tedd,

I'd suggest you start with an Hours matrix report grouped by Hour Owner (vertical) and Entry Date (horizontal, by day) filtered (or prompted) within a specific week, then copy that report and instead group by Project Task on the vertical, rather than Hour Owner.

Regards,

Doug

Translate
Learn more at www.atappstore.com, email doug.denhoed@atappstore.com, or tag me here @Doug_Den_Hoed_AtAppStore.
TeddElAuthor
Nov 11, 2020 2:49 PM UTC

Thanks Doug. I'll give that a try.