I am trying to import a large number of projects from another system using the kickstart. One issue I am having is I have set the setScheduleMode to Completion Date, but the import continually sets it as Start Date. Is there another setting I am missing in order to get the Completion Date set on my import? Thanks. Dave Pond
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

4 replies

Level 9
Mar 29, 2019 1:43 AM UTC
I got this to work for setting the completion date on the project:
Translate
KaliCo1
Level 2
Jun 28, 2022 6:30 PM UTC

On a kickstart, to set the setScheduleMode to be the Completion Date; the only value in the spreadsheet (under that heading) should be C. Just the letter C by itself.

Translate
Madalyn_Destafney
Community Advisor
Community Advisor
Feb 7, 2023 6:34 PM UTC

Hi, I'll d doing a project import from Jira to WF and we use Start Date completion mode - based on this thread, I assume I have S in the column for this? I've never used a kickstart before, any tips on moving projects (with their tasks) from Jira to WF as brand new projects?

Translate
If this helped you, please mark correct to help others : )
Heather_Kulbacki
Community Advisor
Community Advisor
Feb 8, 2023 2:57 PM UTC

@madalyn_destafney yes, you can find the Schedule Mode values in the API Explorer under Projects

https://developer.adobe.com/workfront/api-explorer/

 

 

Translate