Skip to main content
Level 3
May 8, 2023 3:50 PM UTC
Solved

Is there anyway to figure out how long a Project has been on hold (or some other status)?

Is there anyway to figure out how long a Project has been on hold (or some other status)?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Madalyn_Destafney
Madalyn_DestafneyAccepted solution
Community Advisor
May 8, 2023 5:01 PM UTC

Here's an example of filters, if you wanted to pull projects on in a certain status, from a certain date, etc. You'd want to specify the journal entry type is 'edit' to capture status changes.

In your report columns, you can pull the date the entry/change was made.

If you find this helpful, please mark correct to help others : )

If this helped you, please mark correct to help others : )

3 replies

Madalyn_Destafney
Community Advisor
Community Advisor
May 8, 2023 4:58 PM UTC

Hi there! You can use a journal entry report for this, a journal entry report can track changes in field values, statuses, etc. You can filter to only track whatever you need in certain projects if you want, too.

Translate
If this helped you, please mark correct to help others : )
Madalyn_Destafney
Community Advisor
Madalyn_DestafneyCommunity AdvisorAccepted solution
Community Advisor
May 8, 2023 5:01 PM UTC

Here's an example of filters, if you wanted to pull projects on in a certain status, from a certain date, etc. You'd want to specify the journal entry type is 'edit' to capture status changes.

In your report columns, you can pull the date the entry/change was made.

If you find this helpful, please mark correct to help others : )

Translate
If this helped you, please mark correct to help others : )
DaBellAuthor
Level 3
May 8, 2023 6:32 PM UTC

Perfect!  Thank you!

Translate