Is there a way to sort a Project Report on a specific tasks planned completion date?

  • May 28, 2020
  • 2 replies
  • 555 views
No text available
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Level 10
May 28, 2020

Hi Jeremiah, since the only way to pull in a specific task's planned completion date into a project report is via a collection (see the How to Add a Collection to a View article), you will not be able to sort on the value in the column. I'd encourage you to consider creating a task report instead for this purpose. When you pull "Project-level" fields into task reports, you can make them look a lot like project reports to the end users by carefully labeling columns. --Narayan

Doug_Den_Hoed_AtAppStore
Community Advisor
Community Advisor
May 28, 2020

Hi Jeremiah,

In addition to Narayan's suggestion, if the Task level date in question doesn't tend to change very often, another approach would be to create a custom date parameter on the Project itself (e.g. Target Date, or Primary Sorting Date), manually type that date in, and then sort your Project report on that custom data pararmeter.

Crude, but effective; and if worth it, automatable.

Regards,

Doug

Learn more at www.atappstore.com, email doug.denhoed@atappstore.com, or tag me here @Doug_Den_Hoed_AtAppStore.