Is there a way to display the date someone was assigned as project owner in a report?

Project System Activity shows when someone is made the owner of a project.  What is the field name needed to display this data on a project report?

 

 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

4 replies

Scott_Goodwin
Level 3
Mar 12, 2024 10:39 AM UTC

I dont know if its possible. I could be wrong though. 

I would look at a Journal Entry report that will give you the sort of things your looking for. 

Maybe someone has some nice text mode logic you could try.

Translate
SLuna74
SLuna74Author
Level 3
Mar 12, 2024 11:03 AM UTC

I forget about Journal Entry.  Will give that a shot. Thank you!

Translate
Doug_Den_Hoed_AtAppStore
Community Advisor
Community Advisor
Mar 12, 2024 1:11 PM UTC


Hi @sluna74,

 

In addition to the Jornal (or Notes) report idea @scott_goodwin suggested, I invite you to consider this Targeted Auditing technique, which you could use to either track the history of Project Owners, and/or just the current Project Owner’s date of ascension directly in a custom form behind on the Project for easy reference and reporting.

 

Regards,

Doug

Translate
Learn more at www.atappstore.com, email doug.denhoed@atappstore.com, or tag me here @Doug_Den_Hoed_AtAppStore.
SLuna74
SLuna74Author
Level 3
Mar 12, 2024 1:38 PM UTC

Well this is amazing!  I'll give it a try.  Thank you so much!