Is there a way to differentiate a regular project vs a maintenance project. I am looking to create a seperate report for the two types but not sure how to flag them to begin with.

No text available
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Level 10
October 27, 2020
Hi Shawn, I’d place these projects into two different programs within a portfolio. Narayan Raum Workfront COE @ Truist Financial See our new portal for more information.
Translate
Level 2
October 27, 2020

Another way is to create a custom field with a dropdown field containing those two project types: maintenance and regular. This will be reportable. This could be a preferred approach if you have maintenance or regular projects across various programs or portfolios.