Is it possible to create a calendar User based for their tasks? Instead of task list it should show user name and project name.

Hello to All, 😊

Is it possible to create a calendar User based for their tasks? Instead of task list it should show user name and project name.

Appreciate any guidance in this regard.

Best regards,

Kundan.

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
RandyRoberts
RandyRobertsAccepted solution
Community Advisor
April 26, 2022

If you type in a left curly bracket {, you'll get a dropdown of possible fields you can add. In the screenshot I'm selecting project:name preceding task name and assignedTo:name

Here's more:

6 replies

RandyRoberts
Community Advisor
Community Advisor
April 26, 2022

Yes, Just add filters like the pic below. There are some choices to display things a certain way. There is a choice for User Name and for Project Name but not for both. You can combine them in text mode though, I'm sure.

Translate
Kundanism
KundanismAuthor
Level 10
April 26, 2022

Thanks @Randy Roberts‚

I tried but if you refer the below screenshot, I'm missing the code for User Name.

Mvh

Kundan,

Translate
RandyRoberts
Community Advisor
RandyRobertsCommunity AdvisorAccepted solution
Community Advisor
April 26, 2022

If you type in a left curly bracket {, you'll get a dropdown of possible fields you can add. In the screenshot I'm selecting project:name preceding task name and assignedTo:name

Here's more:

Translate
Kundanism
KundanismAuthor
Level 10
April 27, 2022

Thanks a lot @Randy Roberts‚

Extremely helpful. How to know these custom text to use?

Mvh

Kundan.

Translate
Kundanism
KundanismAuthor
Level 10
April 28, 2022

Many thanks @Randy Roberts‚ . I appreciate your guidance in this regard. Have a nice day! 😊