Skip to main content
Christina_Jarosz
Level 9
January 27, 2021
質問

How to filter on tasks with NO predecessors?

  • January 27, 2021
  • 4 の返信
  • 775 ビュー

I know, it seems pretty straightforward. I can filter on tasks with predecessor status. However, for the very first task in a project that has no predecessors - I can't seem to bring that in.

Our report shows status of tasks that the predecessors were completed but it does not show tasks that are not yet started and late.

このトピックへの返信は締め切られました。

4 の返信

skyehansen
Adobe Champion and Community Advisor
January 27, 2021

Can you just filter on Task | Can Start equals true? Or I guess I am asking why are you fixated on predecessors...? (Normally we use "can start" because I think if the predecessors are done it flags the next task as "can start.")

Christina_Jarosz
Level 9
January 28, 2021

Great question! We're trying to be more diligent and making sure our team members check off tasks. So it's still a work in progress and sometimes the next task is ready to start even though the person before them didn't mark their task complete.

We have that captured in our report - however - there is a handful of projects that were a delayed start and since the first task did not start yet (with no predecessor) it doesn't show up on that report.

skyehansen
Adobe Champion and Community Advisor
January 28, 2021

I think I understand what you said?

task | "can start" = true would capture any task with no predecessors as well as any task with completed predecessors.

task | "Task Number" = 1 would capture task number 1

Level 6
January 28, 2021

Hi Christina,

I have used a filter on my reports for Predecessors >> ID = Is Blank - this is a standard option within the report filters list:

Hope that helps! 😉