How to create nested sub task in Workfront by using fusion? | Adobe Higher Education
Skip to main content
Este tópico foi fechado para respostas.
Melhor resposta por lgaertner

Hi,

 

to create a child / subtask, you just need to add the field parentID to your Create Record module and map the id of the parent task to it.

 

Regards

Lars

3 Respostas

lgaertner
lgaertnerResposta
Level 9
March 21, 2025

Hi,

 

to create a child / subtask, you just need to add the field parentID to your Create Record module and map the id of the parent task to it.

 

Regards

Lars

Level 2
March 21, 2025

If I want to create sub task under sub task, is it same way to map?

lgaertner
Level 9
March 21, 2025

Correct, the "sub sub task" would get the sub tasks ID mapped to the parentID field.