Hi,

 

to create a child / subtask, you just need to add the field parentID to your Create Record module and map the id of the parent task to it.

 

Regards

Lars

3 replies

lgaertner
lgaertnerAccepted solution
Level 9
Mar 21, 2025 10:22 AM UTC

Hi,

 

to create a child / subtask, you just need to add the field parentID to your Create Record module and map the id of the parent task to it.

 

Regards

Lars

Translate
Level 2
Mar 21, 2025 11:02 AM UTC

If I want to create sub task under sub task, is it same way to map?

Translate
lgaertner
Level 9
Mar 21, 2025 11:14 AM UTC

Correct, the "sub sub task" would get the sub tasks ID mapped to the parentID field.