How to add Current task(s) and assignee(s) as a column in a project report view WITHOUT having tasks with no assignee show?

I want to see all the current tasks and the primary assignees in a project report view. I've created a text mode column that shows these things BUT it's also pulling in some tasks at the bottom of my projects that are used for deliverable information, these tasks have no assignee so I'm looking for what I could add to my text mode reporting to exclude these tasks without an assignee from the results. 

 

I attempted adding: IF({assignedTo_mod}=notblank but that changed the results to only show current tasks without an assignee (the opposite of what I wanted). 

 

Here's my current code, would love some pointers on what I can do differently to get only current tasks with assignees to show in this column

displayname=Current Tasks listdelimiter= listmethod=nested(tasks).lists textmode=true type=iterate valueexpression=IF({numberOfChildren}=0,IF({canStart},IF(CONTAINS("CPL",{status}),"",CONCAT({name}," - ",{plannedCompletionDate},": (",{assignedTo},")")))) valueformat=HTML
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
NicholeVargas
NicholeVargasAccepted solution
Adobe Employee
Jun 5, 2024 10:49 PM UTC

This should work for you -- it looks for incomplete child tasks that are ready to start and have a user assigned. If true, the column will display the task name - planned completion: assigned to name. 

displayname=Current Tasks listdelimiter= listmethod=nested(tasks).lists textmode=true type=iterate valueexpression=IF({numberOfChildren}=0,IF({canStart},IF({status}!="CPL",IF(!ISBLANK({assignedToID}),CONCAT({name}," - ",{plannedCompletionDate},": ",{assignedTo}.{name}))))) valueformat=HTML

 

3 replies

NicholeVargas
Adobe Employee
NicholeVargasAdobe EmployeeAccepted solution
Adobe Employee
Jun 5, 2024 10:49 PM UTC

This should work for you -- it looks for incomplete child tasks that are ready to start and have a user assigned. If true, the column will display the task name - planned completion: assigned to name. 

displayname=Current Tasks listdelimiter= listmethod=nested(tasks).lists textmode=true type=iterate valueexpression=IF({numberOfChildren}=0,IF({canStart},IF({status}!="CPL",IF(!ISBLANK({assignedToID}),CONCAT({name}," - ",{plannedCompletionDate},": ",{assignedTo}.{name}))))) valueformat=HTML

 

Translate
MatthewLi1
Level 3
Jun 5, 2024 11:05 PM UTC

This is perfect! Thanks so much Nichole.

 