How create a simple report from actual hours vs planned hours for users

Hi WF community,
I have been trying to create a report by team/individual showing the amount of hours worked vs the ones planned. Can anyone guide me with that, I tried using the hours report but didn't get the desired output.

Thanks,

Pk

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
KellieGardner
KellieGardnerAccepted solution
Community Advisor
Mar 2, 2023 4:45 PM UTC

What is the desired output you are looking for? 

 

I like to use assignment reports so it breaks down to planned hours by user vs by task. To get the actual hours I use text mode with the following code:

 

aggregator.displayformat=minutesAsHoursString
aggregator.function=SUM
aggregator.namekey=Actual Hours
aggregator.valuefield=actualWorkCompleted
aggregator.valueformat=compound
displayname=Actual Hours
linkedname=direct
namekey=actualWorkCompleted
querysort=actualWorkCompleted
task=actualWork_Mod=gt
textmode=true
valuefield=actualWorkCompleted
valueformat=compound
viewalias=actualWorkCompleted

 

 

19 replies

Madalyn_Destafney
Community Advisor
Community Advisor
Mar 2, 2023 2:38 PM UTC

Hi there! You can do this with a simple Hour report.

Create a new Hour report, and you can add columns that pull the project planned vs actual (logged) hours or the planned vs actual hours for any object (project, task, issue, etc.). Actual hours is logged hours. 

Then you can add a Grouping to your report to have it by 'hour owner' which is the person that logged the hours (or can do by hour owner home team name if you're looking to do by team.

If you found this useful, please mark this solution correct to help others : )

Translate
If this helped you, please mark correct to help others : )
KellieGardner
Community Advisor
KellieGardnerCommunity AdvisorAccepted solution
Community Advisor
Mar 2, 2023 4:45 PM UTC

What is the desired output you are looking for? 

 

I like to use assignment reports so it breaks down to planned hours by user vs by task. To get the actual hours I use text mode with the following code:

 

aggregator.displayformat=minutesAsHoursString
aggregator.function=SUM
aggregator.namekey=Actual Hours
aggregator.valuefield=actualWorkCompleted
aggregator.valueformat=compound
displayname=Actual Hours
linkedname=direct
namekey=actualWorkCompleted
querysort=actualWorkCompleted
task=actualWork_Mod=gt
textmode=true
valuefield=actualWorkCompleted
valueformat=compound
viewalias=actualWorkCompleted

 

 

Translate
Sep 29, 2023 8:51 PM UTC

Hi, this worked for me as well. However, I would also like to have this field be a field that is available to display in a Chart. For some reason this Actual Hours column/field does not display in the selection and there is not a text mode option to add/view the code.

Any ideas on this?

Translate
Madalyn_Destafney
Community Advisor
Community Advisor
Oct 2, 2023 5:04 PM UTC

You have to apply a grouping in a report before you can have that option in its chart. Chart options in a report are driven from the groupings you apply first. 

Translate
If this helped you, please mark correct to help others : )
KellieGardner
Community Advisor
Community Advisor
Mar 29, 2023 9:54 PM UTC

@pk____  did any of these solutions work for you or do you still need a solution?

Translate
pk____Author
Mar 30, 2023 8:23 AM UTC

Yes, your solution work and we were able to create report thank you.