How can I set a default task constraint for all tasks to be Fixed Dates with simple duration?

No text available
This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

2 replies

Heather_Kulbacki
Community Advisor
Community Advisor
May 1, 2020

HI Howard,

In Setup > Project Preferences > Tasks & Issues you can set the default duration type to Simple. But unless you're creating project templates where all the tasks have a constraint of Fixed Dates, I don't believe there's a way to set a default constraint.

Translate
imgrund
Adobe Employee
Adobe Employee
May 1, 2020

Hi Howard - Yeah, to get fixed dates, you just need your Project Owners to adjust both the start and end dates of the tasks. We have a "one-off" project for resourcing, and as long as you touched both those fields, the task constraint changes.