Does Workfront project condition consider projects not in current status?

  • January 29, 2026
  • 2 risposte
  • 47 visualizzazioni

One of our groups wants to use the idea or planning project status without those projects being considered in the project condition. I can’t find documentation saying if these two statuses are included in this; does anyone have documentation or know the answer?

Thanks!

Questo argomento è stato chiuso alle risposte.
Migliore risposta di Patrick-antegma

Hi ​@NikkiTom,

 

Check the following documentation: https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/projects/manage-projects/project-condition-and-condition-type

Here is an excerpt: Projects that are in any of the following statuses are always marked as On Target, no matter what the dates of the tasks and their progress are:

  • Idea
  • Requested
  • Approved
  • Rejected

All four states below the business case of a project.

 

If you’re in the state “Planning” and something triggers the recalculation of the timeline, the condition will change.

2 risposte

Patrick-antegma
Level 5
January 29, 2026

Hi ​@NikkiTom,

 

Check the following documentation: https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/projects/manage-projects/project-condition-and-condition-type

Here is an excerpt: Projects that are in any of the following statuses are always marked as On Target, no matter what the dates of the tasks and their progress are:

  • Idea
  • Requested
  • Approved
  • Rejected

All four states below the business case of a project.

 

If you’re in the state “Planning” and something triggers the recalculation of the timeline, the condition will change.

Patrick Heinzelmann | 11x Adobe certified | I blog on https://www.antegma.com/en/blog/
NikkiTom
NikkiTomAutore
Level 2
February 2, 2026

Thanks so much for providing this link, Patrick. Very helpful.