Hi,

 

I need the value of a type ahead field that lives at the project level to populate a calculated field at the task level. Is this possible?

 

Project Level = Story Lead (type ahead field.) I need this value to also live on a task under the project. I thought calculated field would be the way to go but it doesn't seem to be working. Can this work? Or is there another solution?

 

Thanks,


Robin

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
RscofidioAccepted solution
Level 2
Aug 28, 2024 2:17 PM UTC

Hi,

 

So I finally asked our implementation consultant (Thanks, @tcraig)

 

The calculation needs to look like this:

 

{project}.{DE:Story Lead:name}
 
So she just added the :name to the end and it worked.
 

2 replies

skyehansen
Adobe Champion and Community Advisor
Aug 21, 2024 1:14 AM UTC

If you can't get it working, try using the same approach as this post:

https://experienceleaguecommunities.adobe.com/t5/workfront-questions/reporting-on-typeahead-fields/m-p/504877

 

Add your calculated field to the project level and then reference that field on the task level.

Translate
RscofidioAuthorAccepted solution
Level 2
Aug 28, 2024 2:17 PM UTC

Hi,

 

So I finally asked our implementation consultant (Thanks, @tcraig)

 

The calculation needs to look like this:

 

{project}.{DE:Story Lead:name}
 
So she just added the :name to the end and it worked.
 