Derive Value from One Task Form to Another with Calculated Field

  • October 5, 2023
  • 2 replies
  • 650 views

Hello! Wanted to see if anyone has any workaround they use in order to get a custom form value on one task to another. The use here is that we want to have users enter information in a task-level custom form (instead of project-level for user experience), but need that same value on to show on another task through a calculated field.

 

Is there any calculated field examples you have used? Not 100% sure this is possible with the hierarchy of the system, but wanted to check anyway!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by skyehansen

You would normally do this in a report using a collection referring to project.tasks... so since calculated fields don't use collections, I wonder if anyone has ever used a custom dashboard on that task as a workaround.

2 replies

skyehansen
Adobe Champion and Community Advisor
skyehansenAdobe Champion and Community AdvisorAccepted solution
October 5, 2023

You would normally do this in a report using a collection referring to project.tasks... so since calculated fields don't use collections, I wonder if anyone has ever used a custom dashboard on that task as a workaround.

VicSellers
Adobe Champion and Community Advisor
Adobe Champion and Community Advisor
October 6, 2023

That's a great idea, thanks for the reply - going to give it a shot.