Cross project predecessorts not automatically calculating

I am seeing that all cross project predecessors have stopped calculating and I have to recalculate timeline to get them to populate, under every circumstance. Is there a setting or something I should know about that would fix this? Otherwise I will open a support ticket.

 

Thanks

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Kurt_Jones
Kurt_JonesAccepted solution
Adobe Champion, Community Advisor, UG Leader
Sep 8, 2022 5:40 PM UTC

There is a global setting under Setup->Project Preferences for recalculating timelines on regular basis

 

If my response answered your question, please mark it answered, so others can find the answer

2 replies

Kurt_Jones
Adobe Champion, Community Advisor, UG Leader
Kurt_JonesAdobe Champion, Community Advisor, UG LeaderAccepted solution
Adobe Champion, Community Advisor, UG Leader
Sep 8, 2022 5:40 PM UTC

There is a global setting under Setup->Project Preferences for recalculating timelines on regular basis

 

Translate
If my response answered your question, please mark it answered, so others can find the answer
JillAcAuthor
Level 10
Sep 29, 2022 4:53 PM UTC

Thanks for this, I did look at this and I would think that changing the predecessor would trigger the recalculation based on the 2nd check box, but it doesn't. I have to refresh the page in order for it to recalculate, every time.