Creating a Template- Duration does not roll up to Parent task from Child Task

I created a New Template and my template durations are not rolling up correctly. I have task constraint set to 'As Soon as Possible'. See attached. I can't figure out why the durations do not roll up to total duration. I have tried everything. 

4 replies

skyehansen
Adobe Champion and Community Advisor
Sep 4, 2025 7:02 PM UTC

I don't see that you've attached anything so feel free to try that part again.

Translate
Sep 4, 2025 7:12 PM UTC

Hi Skyehansen, thank you for bringing this to my attention I have attached the screenshot. 

Translate
Sep 4, 2025 7:11 PM UTC

Translate
skyehansen
Adobe Champion and Community Advisor
Sep 4, 2025 7:15 PM UTC

Can you expand to show all 26 tasks? My feeling is that they aren't adding up because you don't have ENOUGH predecessors linking tasks from one end of the project to the other. By seeing all 26, we can maybe recommend some tasks that you can link to show the continuity of the project timeline.