Hi, I am looking for a way to add a column rule to a task report based on a question in the task details of the prior task.

 

I am pulling a report for "Add photos to the Hub" task, but the prior task is "Fill out details for Hub Request" where there is a custom form on the task details. On that custom form, they have the option to request a rush.

 

I would like my task report for "Add photos to the Hub" to have a column rule if the prior task had rush=yes in the task details. is this possible? 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
skyehansen
skyehansenAccepted solution
Dec 21, 2023 6:13 PM UTC

the only way you would be able to do this would be to set up the prior task as a predecessor of your hub task. Then you could use the Predecessors relationship to set up a rule.

1 reply

skyehansen
Adobe Champion and Community Advisor
skyehansenAdobe Champion and Community AdvisorAccepted solution
Dec 21, 2023 6:13 PM UTC

the only way you would be able to do this would be to set up the prior task as a predecessor of your hub task. Then you could use the Predecessors relationship to set up a rule.