hi 

Im looking for some guidance for a project set up. I have costs against a user, however when when i create a tasks and assign them that to a user the Costs doesn't not show up in the report 😕😕

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Richard_Le_
Richard_Le_Accepted solution
Community Advisor
Oct 10, 2022 8:35 PM UTC

Hi,

 

Have you checked what cost type is associated with the task in the tasks finance settings? If you have a rate associated with the user's profile, the cost type will need to be 'user hourly'. 

 

Regards,

Rich. 

1 reply

Richard_Le_
Community Advisor
Richard_Le_Community AdvisorAccepted solution
Community Advisor
Oct 10, 2022 8:35 PM UTC

Hi,

 

Have you checked what cost type is associated with the task in the tasks finance settings? If you have a rate associated with the user's profile, the cost type will need to be 'user hourly'. 

 

Regards,

Rich. 