Change duration time saved to a template

Good Morning - New to workfront here and I am trying to adjust the duration time saved to an existing template.  Duration days is equal to 1.  I cannot figure out how to change this.  Appreciate your assistance.  Thank you!

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.

1 reply

VicSellers
Adobe Champion, Community Advisor, UG Leader
Adobe Champion, Community Advisor, UG Leader
Jun 10, 2024 12:56 PM UTC

Hi @marydlugo - I might need a little more context, but if you're looking at the template duration and want to change that, then you should navigate to the tasks in the template and change the durations there. Once adjusted, assuming you have the usual settings, it should adjust the overall template duration.

 

Let me know if I didn't answer what you were looking for though!