Looking to view a long task list with just the parent tasks not automatically expended - has anyone found a way to do that?

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Richard_Le_
Richard_Le_Accepted solution
Community Advisor
Feb 8, 2024 9:20 PM UTC

Hi Alyssa,

 

If you click the little arrow next to the task name header in your project view, it will collapse all tasks in your plan under their parents:

 

 

Best Regards,

Rich.

 

2 replies

Richard_Le_
Community Advisor
Richard_Le_Community AdvisorAccepted solution
Community Advisor
Feb 8, 2024 9:20 PM UTC

Hi Alyssa,

 

If you click the little arrow next to the task name header in your project view, it will collapse all tasks in your plan under their parents:

 

 

Best Regards,

Rich.

 

Translate
Level 2
Mar 1, 2024 6:08 PM UTC

This requires a user to collapse it, this is not automatic. Is there a way to have it collapse by default/automatically based on Layout?

 

I tried to do something similar via groupings but it's messy as it includes the parent task with "No Value"